Contruction project are increasingly large and complex in term both of physicals and cost.
Various of project are carried out to meet the increasingly complex of the community needed. Controling
is the process of comparing actual performance with performance to identify irregularities, evaluated,
and take actions accordingly. The cost and time control are part of project management which is
expected to support the project as much as possible. In this case, using the Earned Value Method to
determine the cost and time performance of the weeks as well as the final of the cost and the time of the
project. In this study, the observed data was taken from the construction project building of 11 Pemecutan
Elementary School in Denpasar City.The result showed that the construction project at the end of the
fourth month with a positive value of Schedule Variance (SV) = 113,910,400.46 rupiah which presented
that the project implementation was faster than the planned schedule. While the value of Cost Variamce
(CV) = 258,072,889.18 rupiah with positive Cost Variance shows the cost implementation of the project
is lower than the budget. This result is supported by the value of Cost Perforemance Index (CPI) is 1,184
and the Schedule Performance Index value is 1,074. The result of the Estimated at Schedule (EAS) is 161
days which is faster than the planned time schedule and with the value of Estimated at Completion (EAC)
= 1,805,504,096.19 rupiah. In the end of the project will saving 332,398,875.88 rupiah by the final
project cost

Downloads

Download data is not yet available.
Published
Nov 29, 2020
How to Cite
ASTARI, Desak Made Dwi; SUDIARSA, Made; SUTAPA, I Nyoman. ANALISIS KINERJA PROYEK DENGAN PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN SDN 11 PEMECUTAN DENPASAR. Proceedings, [S.l.], v. 1, n. 1, p. 215-223, nov. 2020. Available at: <https://ojs.pnb.ac.id/index.php/Proceedings/article/view/2238>. Date accessed: 29 mar. 2024.