A construction project plan that had been well-planned often encountered obstacles in its implementation,
it occurred due to the poor management, inappropriate resources, the time schedule which was not in
accordance with the plan, or the inaccurate choice of implementation method. Knowing that there were
some indicators of project achievement, therefore it could be better to pick some alternative implementation
methods which were considered the best. In the construction project of SMAN 2 Abiansemal building which
was located in Sedang Village, Abiansemal, Badung, Bali, it was necessary to choose an alternative
implementation method. This research used a descriptive quantitative research method, which used
measured data, which were primary data; labour productivity & tools, and secondary data; shop drawing,
BOQ (Bill of Quantity), and time schedule. The result showed that the best alternative was by using
scaffolding as the scaffold, 9 mm plywood as the formwork, casting using CP and the addition of working
hours and labours which was assessed from the factors of cost saving, time, quality, availability of materials
and environmental impact. From the analysis result of the alternative using zero-one method, the best
method used was the method that included in alternative II. The cost saving between the existing and the
best alternative was IDR 23,488,183 or 2.21% of the existing and the implementation time, which was faster
for 4 (four) days than the existing one.

Downloads

Download data is not yet available.
Published
Nov 29, 2020
How to Cite
WIRYAWAN, I Nyoman Oka; SUDIARSA, Made; YASADA, Gede. PEMILIHAN METODE PELAKSANAAN PEKERJAAN STRUKTUR DENGAN MENGGUNAKAN METODE ZERO-ONE PADA PROYEK PEMBANGUNAN GEDUNG SMAN 2 ABIANSEMAL. Proceedings, [S.l.], v. 1, n. 1, p. 253-262, nov. 2020. Available at: <https://ojs.pnb.ac.id/index.php/Proceedings/article/view/2245>. Date accessed: 29 mar. 2024.